Device integrations
EMU
Supported devices: EMU Professional II 3/5 TCP/IP energy meter, read over Modbus TCP.
Our EMS reads the EMU Professional II energy meter over Modbus TCP. It can serve as grid meter or as submeter.
The EMU Professional II is available from EMS controller version 0.0.341.
Supported devices
| Model | Description |
|---|---|
| Professional II 3/5 TCP/IP | Three-phase energy meter with a network interface |
Setup
Network
Connect the meter to the same network as the Voltmasters Controller and give it a fixed IP address.
Current and voltage transformers
Set the CT and VT ratios on the meter itself. The meter then reports primary-side values, and there is no ratio to fill in in the EMS.
Add the meter in the platform
Add a device of type Energy meter, with brand EMU and model Professional II 3/5 TCP/IP. Fill in the IP address and the port. The Slave ID is prefilled with
1, the factory default.Verify
Check on the device page that the power and the phase values come in, and that import shows as positive power.
What the meter reports
- Active, reactive and apparent power, in total and per phase
- Voltage and current per phase, and the power factor
- Grid frequency
- Cumulative imported and exported energy
Frozen values
The Professional II sometimes keeps serving the same set of values for up to a minute. The EMS follows the clock of the meter: when that clock has stood still for more than 10 seconds, the EMS stops using the values, so it does not steer on old measurements. After 15 seconds the warning Device data is stale appears on the device. When the meter serves fresh values again, the EMS picks them up by itself.
While the values of the grid meter are stale, the EMS falls back to its safeguards for a missing grid meter, for example the battery stops after a short grace period. When the warning keeps coming back, check the network connection and the firmware of the meter.