DSO RTU
Configuration
Set up Fluvius Fall-Back Flex in the Voltmasters platform, step by step: P_base, P_red, the registered flexible consumption power, day-ahead planning with programs and certificate, the flexible devices and the test.
Fall-Back Flex is configured in the DSO RTU settings, under Configuration → Grid & market → DSO RTU settings, with Fluvius Netflex as provider. It builds on a working Netflex link, see Configuring Fluvius telecontrole.
What you need
| Data | Source |
|---|---|
| P_base (contractual consumption power, kW) | Bid form |
| P_red (reduced power, kW) | Bid form of the awarded bid |
| Registered flexible consumption power (kVA, optional) | Zone sheet (ask the customer) |
| Day-ahead steering required: yes or no | Zone sheet |
| Asset point id and program ids | Fluvius (only with day-ahead steering) |
| Client certificate and private key | Customer, see Planning certificate (only with day-ahead steering) |
Start the certificate first when the zone requires day-ahead steering: it has the longest lead time.
Step by step
Enter P_base in the grid settings
Under Configuration → Grid & market → Grid settings, set the consumption access power to P_base from the bid form. It is the 100 % reference of every Fluvius limit. Without it, Fall-Back Flex cannot steer.
Check technical flex
Leave Enable technical flex off for a connection with only Fall-Back Flex. Switch it on only when the study document also includes technical flex, see Technical flex.
Enable Fall-Back Flex
Switch Enable Fall-Back Flex on, enter P_red and enter the Registered flexible consumption power from the zone sheet when you have it. Check the flexible volume the form shows against the bid form.
Set up day-ahead planning (when required)
Switch Enable day-ahead planning on, enter the asset point id, map the programs and upload the certificate and the private key. Each field is explained under Day-ahead planning.
Make the flexible consumption controllable
Add the battery, the EV chargers and the controllable loads under Configuration → Devices, each with its nominal power. Set the order in which the controller holds them back under Load shedding priorities: the batteries always come first, then the groups in that order. Without a saved order, the controller uses a fixed order and the loads go by their Priority: 1 is switched off last. See How an activation works. Check that channel 6 in the Netflex measurement channels covers the registered flexible consumption power.
Save and check the controller
Save the form. The controller picks up the settings within a minute. If its software is too old for Fall-Back Flex, the form and the Fall-Back Flex page say so: update the controller first.
Test
Ask Voltmasters support for a test limit (for example 80 %) and follow it on the Fall-Back Flex page: the net consumption must be below the limit within 3 minutes. Then plan the commissioning test with Fluvius (reason code 99), see Commissioning & certification.
What Fluvius watches during an activation
Fluvius settles on the billing meter, but the Netflex cabinet also watches channel 6 (flexible consumption): during a limit, that is where Fluvius expects the power to drop.
| Channel | What goes in it |
|---|---|
| 6 | Everything the zone sheet counts as flexible consumption, the battery included. |
| 5 | EV charging. |
| 1, 2, 3, 4 and 7 | Nothing without technical flex: the asset channels stay empty. |
The channel per device is set in the Netflex measurement channels, which also compare channel 6 with the registered flexible consumption power.
Classic mistake: channel 6 well below the registered power. Fluvius then sees only part of the volume drop and counts the service as not delivered, even though the site did reduce.
Fall-Back Flex

P_base comes from the grid settings, P_red from the bid.
| Field | What to enter |
|---|---|
| Enable Fall-Back Flex | On when this connection takes part in Fall-Back Flex. |
| P_base (contracted consumption power) | Read-only, from the grid settings. If it is missing, the form links to the grid settings. |
| P_red (offered power limit) | The reduced power of the bid, in kW. It must be below P_base. |
| Registered flexible consumption power (optional) | The flexible consumption power the zone sheet registers for channel 6, in kVA. The EMS does not steer on it: the form checks channel 6 of the Netflex measurement channels against it. Left empty, only that check is skipped. |
When a desired monthly peak (consumption) caps the import limit below P_base, the form warns about it. The EMS then applies the Fluvius percentage to that lower value, so during an activation it holds consumption lower than Fluvius ordered. Check whether the desired monthly peak is still needed.
Day-ahead planning

Day-ahead planning: asset point id and one program per steering product.
| Field | What to enter |
|---|---|
| Enable day-ahead planning | On when the zone sheet says "Mandatory implementation of day-ahead steering: yes". The fields below only appear then. |
| Asset point id | The asset point Fluvius linked the certificate to. |
| Planning API base URL | Leave empty. Only fill it in when Fluvius gives you another URL. |
| Programs | Every program id Fluvius announced, with its Reference power: Connection point or Assets. See Programs. |
| Client certificate (PEM) | The certificate Fluvius registered. |
| Private key (unencrypted PEM) | The key that belongs to the certificate. |
| CA certificate of the Fluvius server | Optional. |

After the upload only the thumbprint and the expiry date are shown.
On upload the platform checks that the certificate is readable, not self-signed and not expired, that the key has at least 2048 bits and that it matches the certificate.
Switching day-ahead planning off deletes the asset point id, the programs and the stored certificate. Switching Fall-Back Flex off clears P_red.