Skip to content

Configuration

Configure a Voltmasters microgrid: the microgrid settings and thresholds, the IO roles on the IO module, the generator settings and the load shedding priorities.

A microgrid is configured in four places on the project.

Before you start

  • The project's controller runs a firmware version that supports Microgrid. Until then the settings below stay hidden.
  • The devices are added: the battery (PCS), the IO module and, if present, the generator and the PV inverters. See Adding and verifying devices.
  • You are a Voltmasters administrator or have the Installer role on the project.

Microgrid settings

Open Configuration → Grid & market → Microgrid settings. One Save at the bottom stores the whole page and sends it to the controller.

Voltmasters EMS: the top of the Microgrid settings with the Microgrid operation switch, the Grid transfer setting and the Generator group of thresholds, including the reactive power takeover

The top of the page: the main switch, the grid transfer and the generator thresholds.

SettingMeaning
Microgrid operationSwitches the microgrid logic on the controller on or off. The IO roles can be assigned and tested while it is off; the controller only acts on them once it is on.
Grid transferWho performs the transfer between grid and island. On a site with a grid connection, choose The EMS performs the transfer: a static transfer switch is not supported. For an off-grid site, choose No grid connection, the site only runs as an island: then there is no transfer, the Grid window and Reconnection groups, the island reserve and generator support with the grid present do not apply and are hidden, and the PV cannot be set to Disconnect while islanded, as that would keep it off for good.
Voltmasters EMS: Microgrid settings of an off-grid site, with Grid transfer set to No grid connection, the site only runs as an island, and a Generator group without the generator support with the grid present

A site without a grid connection: the settings that need a grid are left out.

Thresholds and policies

They apply as soon as microgrid operation is on.

GroupSettingDefaultMeaning
GeneratorStart SOC (%)20Below this state of charge the controller starts the generator.
Stop SOC (%)90Above this state of charge it stops the generator again. Must be above the start threshold.
Generator support with the grid presentOffLets the generator support the site on the grid too, for example to shave a peak. Off: it only runs in island operation.
Reactive power takeoverOffIn an island, the battery converters take over the reactive power a generator running in parallel delivers, so no reactive power circulates. Island operation only. Switch it on only once a test on site confirms the battery converters follow their reactive power setpoint.
Reactive power takeover per second0.05The share of the generator’s reactive power the battery takes over each second, between 0.01 and 0.2.
Reactive power dead band (kVAr)5Within this band the generator counts as delivering no reactive power.
Grid windowMinimum grid voltage (V)207Outside this window the grid does not count as usable.
Maximum grid voltage (V)253
Minimum grid frequency (Hz)49.5
Maximum grid frequency (Hz)50.5
Grid stable for (s)60How long voltage and frequency must stay inside the window before the grid counts as returned.
AC busConfirm a dead bus after (s)10How long the bus must stay without voltage before the controller considers it dead.
Bus meterNoneAn energy meter on the AC bus the controller reads the bus voltage from, for a site without the AC bus voltage present input. With that input wired as well, both have to agree. On a site with a grid connection the grid meter cannot serve: it measures the grid side of the breaker.
Generators confirm a dead busOffLets the busbar measurement of the generators also confirm a dead bus, after which the site may close a breaker onto it. Switch it on only once a test on site shows that every generator reads a dead bus as dead with its engine stopped.
ReconnectionReconnectionManualManual (release from the app) waits for a release. Automatic reconnects on its own. See Grid reconnection.
Automatic reconnection delay (s)60Only with Automatic: how long the controller waits after a stable grid.
Synchronised reconnectionOffReconnects without an interruption through a synchrocheck relay, only where the EMS performs the transfer. See Synchronised reconnection.
Slip above the grid (Hz)0.025Only with synchronised reconnection: the slip at which the EMS holds the island above the grid frequency, the window the synchrocheck relay is set to, and how long one attempt may take.
Relay voltage window (%)5
Relay phase window (degrees)5
Relay observation time (s)0.5
Time per attempt (s)420
Islanded operationPV while islandedLimitLimit keeps the inverters online under a setpoint. Disconnect takes them off the AC bus (needs a PV relay, see below). Unavailable: the PV cannot be steered and stays off.
Power reserve (%)10Share of the available power kept free to absorb a sudden load.
Start load shedding at SOC (%)30Below this state of charge the controller starts shedding loads.
Island reserve SOC (%)50On the grid the battery does not discharge below this, so energy is ready for an outage. Topped up from the grid at any price. 0 turns it off.
PV limit (% of forming power)76In an island the battery forms: the most the PV and the production the controller cannot curtail (such as wind) may deliver together, as a share of the rated power of the battery converters forming the island. A forming converter has to take up a load that drops away at once, faster than the PV can be curtailed. Only shown while PV while islanded is set to Limit.
Voltmasters EMS: microgrid settings with the AC bus group, with a bus meter selected, and the Reconnection group set to manual release with synchronised reconnection off

The AC bus with a bus meter, and the reconnection.

IO roles

In the Microgrid section at the bottom of the page you assign every signal to a port of the IO module: pick the IO extension and the Port. For outputs you also choose the Actuation: Level (hold) or Pulse, with a Pulse duration (s) (5 s by default).

Voltmasters EMS: IO roles for the inputs, each with an IO extension, a port and an Inverted switch, with the grid breaker feedback on digital input 0 of the IO module

Inputs: per signal the IO extension and the port, and the Inverted switch.

By default an input reads a high signal as the condition holding. Switch on Inverted for a contact that opens when the condition holds, such as a relay that drops when the breaker closes. That needs controller version 0.0.339-14 or later. Check on site that the role reads the condition exactly while it holds.

RolePort
Grid breaker closed (feedback), requiredInput
Decoupling switch closed (feedback)Input
Protection relay trippedInput
Emergency stop from microgrid controllerInput
AC bus voltage presentInput
Grid breaker: closeOutput
Grid breaker: openOutput
Grid breaker: release (high = breaker may close)Output
Decoupling switchOutput
Generator startOutput
Emergency stop to microgrid controllerOutput
PV disconnect (high = PV off) or PV release (high = PV allowed)Output
Voltmasters EMS: IO roles for the outputs, with Grid breaker: close on a digital output with pulse actuation of 5 seconds

Outputs: the breaker close command as a 5-second pulse.

  • One port carries one role, and one role sits on one port.
  • Use either PV disconnect or PV release, not both. Both only work with level actuation.
  • Close the grid breaker with Grid breaker: close or with Grid breaker: release, not both. The release only works with level actuation, needs the Grid breaker closed (feedback) feedback and a port whose relay gives it while energised (NO-ON or NC-OFF). It needs controller version 0.0.339-14 or later.
  • A relay that carries a microgrid role cannot be tested from the device page. Remove the role first.

Generator settings

The generator's own limits are set on the generator device: open Devices, choose the generator and go to its settings. The supported engine controllers are the DEIF AGC 150 and AGC 200. The AGC 200 needs controller version 0.0.339-11 or later.

SettingMeaning
Rated powerThe generator's rated power in kVA. Required.
Ramp rateHow fast the generator may change its power, in % per second. Required: without it the controller does not dispatch the generator.
Minimum load / Target loadThe lowest load the generator may run at (30 %) and the load it aims for (80 %).
Minimum runtime / Minimum off timeIn minutes, to avoid short start and stop cycles.
Fuel price per literThe price of one liter of fuel, in €. The microgrid report multiplies it by the liters the generator used.
Fuel consumption at 50% load / Fuel consumption at 100% loadIn liters per hour, as on the datasheet of the generator. Enter them together; the consumption at 100% load must be higher than at 50%. When the engine controller has no fuel counter, the microgrid report estimates the liters used from them.
Fuel cost per produced kWhIn € per kWh. Only used without a fuel price per liter, or when the report can neither measure nor estimate the liters.
Start-up costIn € per start.
Backup generatorThe generator only starts when no other generator of the site can run: none reports ready to start, a start failed, it cannot be read or it is held stopped. Once another generator is back on the bus, the backup generator stops again after its minimum runtime. Leave it off on the main generator.
ControllableOff: the controller only reads the generator (monitoring) and sends it no commands. Use this when another system controls the generator.
Auxiliary energy meterAn energy meter on the cable of the generator that the controller uses to measure its power, more precisely than the engine controller. Set the meter's metering direction to Inverted when it books the generator's delivery as import.

Load shedding priorities

Open Configuration → Strategy and scroll to Load shedding priorities. The order applies project-wide, to the grid limit protection and to island operation.

Voltmasters EMS: load shedding priorities with two EV chargers in priority group 1, a heat pump in group 2 and cold storage under Critical: do not shed, and the check that the batteries can carry the critical loads

EV chargers are shed first, then the heat pump. The cold storage is critical and stays on.

  • Priority group 1 is limited first, group 2 only when group 1 is not enough. Drag devices between groups or use the menu on a device. Within a group, the controller limits EV chargers before switched loads.
  • Critical: do not shed: these devices are never shed, on the grid nor in island operation. Only an emergency stop from the grid operator still switches them off.
  • The battery sits outside the groups: on the grid it is always limited first, in island operation it forms the grid.
  • With Microgrid on, the top of the list checks whether the batteries can carry the critical loads in island operation (battery power minus the power reserve).

The order only reaches the controller once you click Save priorities. As long as the list shows Default order, the controller uses its own default order: EV chargers first, then the other loads.