Rule builder

Build your own logic for a Voltmasters EMS project in the rule builder: the nodes per category, saving a draft, publishing, the history, the live view and the limitations.

With the Rule builder you draw your own logic for a project: when this happens, do that. You connect inputs, such as a contact on an IO module or the state of charge of a battery, through functions to actions, such as switching a relay output or overriding a device. The result is a flow that the EMS controller on site runs by itself, also when the internet connection is down.

You find it in a project under Configuration, Rule builder.

The rule builder of a project: the canvas with a flow of five connected nodes, the tabs of the flows at the top, the Live view button, the version name with Save as Draft and Publish, and the Nodes tab on the right with Inputs, Functions and Actions.

The rule builder: the canvas in the middle, the nodes on the right, saving and publishing at the top.

Who can use it

  • The installer of the project and the partner the project belongs to can build, save and publish flows.
  • Clients and viewers of a project cannot open the rule builder.
  • The project needs an EMS controller with a software version that runs flows. Without a controller, or with an older version, the rule builder is not in the menu.

How a flow is built

A flow is made of nodes that you connect from left to right. There are three kinds:

Kind What it does
Inputs Bring a value into the flow. An input has no incoming connection.
Functions Combine, compare or delay what comes in and pass the result on.
Actions Do something on the installation. An action has no outgoing connection.
  1. Add nodes

    Drag a node from the Nodes tab on the right onto the canvas, or click it.

  2. Configure each node

    Click a node and fill in its settings in the Configuration tab: the device, the port, a threshold or a time window. A node that is not complete yet has a dashed border.

  3. Connect the nodes

    Drag from the dot on the right of a node to the dot on the left of the next one. The rule builder refuses a connection that cannot work and tells you why.

  4. Save or publish

    Use Save as Draft to keep your work, or Publish to send it to the controller. See Draft and publish.

The rule builder with the Threshold node selected. The Configuration tab on the right shows its settings: activation threshold 40, deactivation threshold 25 and edge pulse duration 1 second, with the buttons Duplicate node and Delete node.

Click a node to fill in its settings in the Configuration tab.

Two connected nodes. The IO Module node is complete. The Set Output node has a dashed border and an orange exclamation mark, because no output is chosen yet.

A node that is not complete yet has a dashed border and a warning mark.

A project can hold several flows. Each flow has its own page: add one with Add page and double-click its name to rename it. All pages are saved and published together as one version.

The nodes

Inputs

Node What it gives
IO Module The state of a digital input of an IO module: on or off.
Battery A value of a battery, such as the state of charge.
Device measurement A live measurement of a device in the project, such as power, energy or state of charge.
Schedule On during the time windows you set, per day of the week. A window that ends at 00:00 runs until the end of the day.
Incident On while an incident of the chosen type is active.

Functions

Node What it does
AND, OR, XOR On when all inputs are on, when at least one is on, or when exactly one is on.
NOT Inverts its input.
Greater than, Less than, Greater or equal, Less or equal Compares a number with a fixed threshold or with a second input, and gives on or off.
Threshold Switches on at one value and off at another (hysteresis), so the output does not flicker around a single limit.
Switch Remembers its state: one input switches it on, the other switches it off. Off wins when both are active.
Pulse At Gives a pulse of a set duration at a time of day or on a date.
Delay Waits the set number of seconds before it passes the signal on.

Actions

Node What it does
Set Output Switches a relay output (DO) of an IO module on or off.
Incident Creates an incident of the chosen type, or resolves it.
Override Applies a control override to a device, such as a power limit, for as long as its input is on.

An action needs an on or off signal. A number, such as a state of charge, first goes through a comparison or a Threshold node.

Examples

Five small flows to start from, as they look on the canvas. Each one reads from left to right: inputs on the left, functions in the middle, actions on the right. The devices, ports and values are examples: choose your own in the configuration of each node.

A contact switches a relay

The simplest flow: an input wired straight to an action. Here a fire alarm contact on a digital input switches a relay output, for example for a signal lamp.

A flow of two nodes: the IO Module input Fire alarm contact on DI 0 is connected to the Set Output action Signal lamp on.

The relay output is on for as long as the contact is closed.

Report a door that stays open

A Delay filters out short signals. The incident is only created when the door contact has been on for a full minute.

A flow of three nodes: the IO Module input Door contact on DI 1, a Delay of 60 seconds and the Incident action Report open door, which creates an incident.

Opening the door for a moment does nothing. After 60 seconds an incident appears in the project.

Discharge the battery during the evening peak

Two conditions that must both be true go through an AND. The Threshold turns the state of charge into on or off, with a margin so the battery does not start and stop around one value.

A flow of five nodes: the Schedule input Evening peak goes to an AND. The Battery input Battery SOC goes through a Threshold with Von 40 and Voff 25 to the same AND. The AND is connected to the Override action Discharge 10 kW on PCS 1.

On weekday evenings the battery discharges at 10 kW. It starts once the state of charge is at 40 % and stops when it drops to 25 %.

Charge at night until the battery is full

A comparison followed by a NOT gives not full yet. Together with the night window it decides when to charge.

A flow of six nodes: the Schedule input Night tariff goes to an AND. The Battery input Battery SOC goes through Greater or equal 90 and a NOT to the same AND. The AND is connected to the Override action Charge 5 kW on PCS 1.

At night the battery charges at 5 kW until its state of charge reaches 90 %.

Stop charging while the grid limit is exceeded

An incident can also start a flow. Here the battery stops charging for as long as the grid consumption limit is exceeded. The override ends by itself when the incident is resolved.

A flow of two nodes: the Incident input Grid limit exceeded, for any device in the project, is connected to the Override action Stop charging, which sets the charge power of PCS 1 to 0 kW.

As long as the incident is active, the charge power of the battery inverter is held at 0 kW.

Draft and publish

Button Effect
Save as Draft Keeps your work on the platform. Nothing changes on the installation. A project has one draft at a time.
Publish Checks all flows, sends them to the EMS controller and makes them the version that runs. The previous version moves to the history.

You can give a version a name before you save or publish it, for example Fire alarm relay. That makes it easier to find back later.

Before publishing, the rule builder checks the flows and lists what is wrong, per node. Until every point is solved, the flows are not published.

A published flow switches real equipment. Check the outputs and overrides of a flow before you publish, and follow the first run in the live view.

History

History lists every version of the project: the draft, the current version and the earlier ones, each with who published it and when.

  • View opens an earlier version read only.
  • Revert copies an earlier version into the draft. It does not run yet: review it and publish it.
  • Delete draft removes the draft. The published version keeps running.

Live view

Switch on Live view to see what the flows do on the controller right now:

  • Active nodes get a green outline and inactive nodes fade out.
  • A delay that is counting down gets an amber outline.
  • Green connections carry an active signal.
  • Inputs show the value the controller reads.

The live view shows the published version. Changes you have not published yet are not running, and the rule builder tells you so.

Limitations

  • Flows run on the EMS controller. A project without a controller, or with a controller version that does not run flows yet, cannot use the rule builder.
  • A relay output that is already used by a controllable load, telecontrol, an alarm signal or the microgrid cannot be switched by a flow. Choose another output.
  • Two Override nodes that change the same setting of the same device conflict when both are active. The rule builder warns you: make sure they are never on at the same time.
  • A flow may not create the incident type that also triggers it. That would switch the flow on and off endlessly, so it is refused.
  • A node that needs a newer controller version than the project has is greyed out in the list, with the version it requires.
  • An override from a flow follows its input: it ends when the input goes off.